Today work has recommenced on our new two storey building after the two-week shutdown period of the construction industry. We can still only have 25% of the normal construction workforce on our site, with this changing to 50% by next Tuesday.

Brickwork has commenced, Colourbond external wall cladding to commence over next fortnight, services rough in ongoing (approximately 60% complete), wall lining commenced and joinery wall lining ongoing.