During the second half of Term 2 we completed the sketch design process with the architects for our three new buildings – Performing Arts Centre and Canteen, PE multipurpose stadium and Year 8 Learning Centre. These plans are up in the staffroom and I am happy to show these to any parents who are interested next time you are in the school. These were submitted to the Department along with the sketch design report and cost plan B at the end of term.
We now have to wait for this stage to be formally approved by the Department before moving on to the design development phase. The design development stage will take us through most of Term 3, and the design development report and cost plan C again needs to be submitted to the Department for approval before we move to construction documentation and putting the project out to tender which we anticipate will happen in Term 4.
Michelle Roberts